This is part of a series of articles looking at The Digital Plan of Work
The RIBA Plan of Work was initiated in 1963 as a framework for architects to use on projects. Over the years, it has become an industry-wide tool. It explains the expected outcomes, core tasks and information exchanges throughout the life of a construction project.
The 2020 version of the Plan of Work includes an ‘Information Exchanges’ taskbar, as shown below in Figure 1. The information produced at the end of a stage then influences the decisions and the work required throughout the next stage. For example, the ‘Business Case’ at the end of Stage 0 then informs the ‘Project Budget’ that is developed as part of Stage 1. With respect to the more structured information requirements, the ‘Responsibility Matrix’ and the ‘Information Requirements’ delivered at the end of Stage 1 are critical to the success of the project.
Figure 1.1 - The ‘Information Exchanges’ taskbar within the RIBA Plan of Work.
(Click the image to see in more detail)
Although this article focuses on the planning and delivery of information requirements, the wider aspects of the RIBA Plan of Work are covered in the free ‘Overview’ guide. The guide looks at three main areas:
Download The RIBA Plan of Work Overview
As part of the launch of the RIBA Plan of Work 2013, NBS and the RIBA worked together with respect to the digital aspects of the Plan of Work. NBS also worked with RIBA and other industry bodies to develop an online digital plan of work tool as part of the Innovate UK-funded BIM Toolkit. NBS and RIBA worked closely together to align both.
The online version within the BIM Toolkit was retired in June 2022. NBS recommends using the RIBA Plan of Work Toolbox for defining who is in the project team and what each party in the project team needs to do. The Toolbox contains template content for a ‘Project Roles Table’, a ‘Responsibility Matrix‘and ‘Multidisciplinary Schedules of Services’. The Responsibility Matrix allows for the planning of aspects of design, giving clear responsibility for delivery at each stage, and indicators for level of detail (LOD) and level of information (LOI).
Clarity is also needed on where the design responsibilities lie between the design team and any specialist subcontractors. This is not the same as simply setting the procurement route. Traditional projects may have elements of specialist subcontractor design where descriptive information is needed. Equally, design-and-build projects may have elements of prescriptive information where the client would like the design team to have responsibility for certain system and product decisions. With this in mind, it is essential that a Responsibility Matrix is set up prior to the design stages of a project. Clearly, the Responsibility Matrix will be updated as the project progresses, and it is essential that this is reviewed at the start of the technical design stage of a project (RIBA Stage 4) so it is clear who is producing the final information for construction.
The screenshots below illustrate how a Responsibility Matrix in the RIBA Plan of Work Toolbox may develop throughout the project timeline. Click to view a larger version of each screenshot.
Figure 2.1 shows an example Responsibility Matrix within the RIBA Plan of Work Toolbox developed prior to the design stages. This considers the design practice ABC Architects planning the design prior to the procurement strategy being known. Note that:
Figure 2.1 – Example Responsibility Matrix within the RIBA Plan of Work Toolbox, developed prior to design stages
(Click the image to see in more detail)
Figure 2.2 shows the same example Responsibility Matrix prior to the technical design stage of the project. This example demonstrates a design-and-build project, where the main contractor has not novated ABC Architects, and the designers (DEF Architecture) are now part of the design team. The specialist subcontractor XYZ Roofing is now also named. Note that:
Figure 2.2 – Updated Responsibility Matrix prior to technical design stage
(Click the image to see in more detail)
Figure 2.3 shows the same example specification summary sheet within NBS Chorus prior to the technical design stage of the project. This shows how expert platforms such as Chorus can add further detail over and above the Responsibility Matrix developed in tools such as Microsoft Excel or Google Sheets. Note that:
Figure 2.3 – Specification summary sheet in NBS Chorus reflecting information requirements detailed in the Responsibility Matrix
(Click the image to see in more detail)
At the end of the technical design stage, final requirements for handover information will be known. The specification itself will list these system completion tasks and information requirements. A master information delivery plan should then be developed to reflect these requirements, and in this further LOD and LOI bandings for the construction and handover stages of the project may be referenced.
The RIBA Plan of Work is intended as a multidisciplinary tool that is used by the lead designer. Further discipline-specific guidance is provided by other institutions. These are linked to below:
The RIBA Plan of Work sets out the need for clear information exchanges and the responsibilities for delivery, but does not provide guidance in terms of more detailed information management. The resources at the UK BIM Framework website sets out the approach for implementing BIM in the UK using the framework for managing information provided by the ISO 19650 series. It includes: the published standards called upon to implement BIM in the UK; the UK BIM Guidance Framework; and useful links to other resources.
https://www.ukbimframework.orgThis article has focused on good information management and clearly defined responsibilities. However, these are enablers to deliver against client requirements and the project outcomes.
When the RIBA Plan of Work 2020 was published, NBS worked with the RIBA Plan of Work team to jointly run a set of webinars introducing the Plan of Work and also the core project strategies to deliver successful outcomes against client requirements.
These webinars can all be accessed ‘on demand’ at the links below: