Dr Stephen HamilIn June 2011 the UK government published its Building Information Modelling (BIM) Working Party Strategy. This report announced the Government's intention to require collaborative 3D BIM (with all project and asset information, documentation and data being electronic) on its projects by 2016. The software and data requirements for this detailed in the report are Construction Operations Building Information Exchange (COBie).

In this article, Stephen Hamil examines COBie and discusses the role of CAD and master specification systems in creating this data model. This article is aimed at construction professionals who work on government projects and clients in the private sector interested in this approach.

Introduction

What did Paul Morrell, Chief Government Construction Advisor, mean when he said "For the first year, the total software requirement is Excel" when discussing the Government's commitment to BIM on construction projects at the NBS BIM Roundtable?

"For the first year, the total software requirement is Excel"
Paul Morrell, Chief Government Construction Advisor

He was talking about COBie – a spreadsheet data format that contains digital information about a building in as complete and as useful a form as possible. In short, COBie is a Building Information Model (BIM).

An exact definition of COBie is included in Appendix 10 on page 59 of the Strategy Paper for the Government Construction Client Group, published in March 2011. An Implementation and Mobilisation Task Group is now establishing how the COBie methodology can be tailored for Government requirements.

Looking further at this strategy paper it reads:

"5.5 Improved Information Handover
In order to improve the measurement and management of public assets, it is recommended that public clients request that specific information be delivered by the supply chain. The specified information set, called COBie, delivers consistent and structured asset information useful to the owner-operator for post-occupancy decision-making."

COBie was developed by a number of US public agencies to improve the handover process to building owner-operators. It is, typically, a Microsoft Excel spreadsheet, but other spreadsheet applications may be used.

The data inside a COBie spreadsheet

In a typical construction project the information about the building is contained in drawings, bills of quantities and specifications. A number of construction professionals normally collaborate to put this documentation together. The documentation should then be updated through the construction phase and handed to the client. In reality, this does not always happen, or when it does, the documentation is supplied in a format such as PDF or paper that makes it very difficult for the client to use.

The idea behind COBie is that the key information is all pulled into one format and shared between the construction team at defined stages in a project. The green circles from the illustration in Figure 1 below shows when the data in COBie format is required and what the client benefit is.

Figure 1- Illustration from the Strategy Paper for the Government Construction Client Group

Figure 1- Illustration from the Strategy Paper for the Government Construction Client Group

Nick NisbetI recently spoke to Nick Nisbet, the co-author of the COBie2 format; he explained: "The argument that drives the demand for COBIe is the management of 'space usage', 'operations', 'cost and environmental impacts', 'repair' and 'replacement' . In short, better value, cost and carbon."

 

 

Mark BewI also discussed this with Mark Bew, the co-chair of the team that authored the strategy paper, and he explained why improved construction data is essential: "The strategy is all about using BIM and re-usable information to enable cost and carbon reduction. COBie is simply the exposure and exchange format we have selected for non-graphical data at level 2 [see Figure 2 below]. The reasons for selection were pragmatics around cost, availability and forward compatibility with IFC to start the process of building a useful built asset legacy dataset."

Figure 2- The Bew-Richards BIM Maturity Model

Figure 2- The Bew-Richards BIM Maturity Model

A colleague of mine uses a jigsaw puzzle analogy to explain BIM; as this information is from many sources, it can be thought of as a jigsaw puzzle that makes up the building - see Figures 3 and 4. Some of the pieces live in the CAD model, some in the specification model and some may exist in other spreadsheets and word processing documents.

Figure 3 - A BIM with just the information from the CAD model

Figure 3 - A BIM with just the information from the CAD model

Figure 4 - A full BIM contains all of the construction information about the building

Figure 4 - A full BIM contains all of the construction information about the building

A COBie spreadsheet is by no means a full BIM, but it does contain structured content from all members of the construction team and from many information models as shown in the screenshots below. Figure 5 shows one of the worksheets that define the floors, spaces and zones that make up the building. Spaces can exist on Floors. Groups of Spaces can also be categorised in Zones. This information would typically be extracted from the CAD model.

Figure 5 - The 'Floor' worksheet within a typical COBie spreadsheet

Figure 5 - The "Floor" worksheet within a typical COBie spreadsheet

Figure 6 shows an example "Type" worksheet. This is information that would usually be extracted from the specification and lists the types of products in the building, their reference and contact information for the manufacturer. Not shown is the "Attribute" worksheet; this details the properties for each of the type objects. An example of this would be the colour and the material of the bath item in Figure 6 and any standards it conforms to.

Figure 6 - The 'Type' worksheet within a typical COBie spreadsheet

Figure 6 - The "Type" worksheet within a typical COBie spreadsheet

Each instance of these type objects are then detailed in the "Component" worksheet. This is shown in Figure 7 where the Doorset instance DSA-001 is of Doorset Type A and is in space F2-002. This information would come initially from the CAD model and be then linked to the type information from the specification model.

Figure 7 - The 'Component' worksheet within a typical COBie spreadsheet

Figure 7 - The "Component" worksheet within a typical COBie spreadsheet

The "Contact" worksheet lists contact details, company information and company roles. This would list a wide range of contacts from the design consultants to the construction team to the manufacturers and suppliers of the systems and products. This information would all typically come from the specification and preliminaries. An example of this worksheet is displayed in Figure 8.

Figure 8 - The 'Contact' worksheet within a typical COBie spreadsheet

Figure 8 - The "Contact" worksheet within a typical COBie spreadsheet

The spreadsheet also has worksheets such as the "Job" worksheet that allow specific facility management tasks to be assigned to the various objects in the building. This is shown in Figure 9.

Figure 9 - The 'Job' worksheet within a typical COBie spreadsheet

Figure 9 - The "Job" worksheet within a typical COBie spreadsheet

Within the spreadsheet it is possible to link the data. So, for example, the window instances can be linked to the specification of the window type through a simple drop down box. Equally when an FM task is assigned, it can be assigned to the relevant component.

NBS and COBie

COBie is a collaborative effort: no one professional or trade organization will have all the information, so cut-and-paste is the minimum skill. However, at NBS, our new master specification product for the UK is embracing BIM and interoperability to open standards. It is being "built for BIM". So, for release later this year, there will be an option to export to a format that can be easily added to a COBie spreadsheet. The screenshot below shows the how this information is exported.

NBS export options

This ensures that information from the specification and preliminaries models can be added quickly and accurately to a spreadsheet for the client. By providing this export functionality from NBS, a huge amount of data can be incorporated on a COBie spreadsheet by those using NBS to write their project specifications.

Find out more

NBS are members of "buildingSMART" and are committed to working to open standards for information collaboration in construction. http://www.buildingsmart.com/

For more information on the COBie data format including schemas and example content see: http://www.wbdg.org/resources/cobie.php

(Thanks to Bentley Systems' Volker Thein for the help with the screenshots)

Stephen is currently blogging about how NBS is embracing BIM at: http://constructioncode.blogspot.com/search/label/NBS Create

Join Stephen's LinkedIn network: http://uk.linkedin.com/in/stephenhamil/.

Related NBS information:

Articles:

September 2011

 

Forthcoming NBS conferences and seminars

NBS Live: Digital Thinking, Smart Building
Offering an impressive programme of over 60 speakers, 26 hours of seminars and four key subject areas: BIM, Design, Sustainability and Business and Practice. find out more...

 

ViewAllArticles

BackToTop

Email Updates

Receive regular email
updates from NBS

Follow @TheNBS on Twitter

Buy This Book

BIM Demystified (2nd edition)

 
Available now from
RIBA Bookshops

BuyNow