Value engineering - time to change our approach

Value engineering - time to change our approach

Dec 3, 2018 |NBS

Picture this

You’re a designer in construction, and you work for months designing a facility; spending time not only making sure that every element is considered but how they all work together. You can only do this using the knowledge and information you have for that stage of the project, but you’re confident that you and the other designers have a good all-round solution.

Then, someone comes along and tells you to change parts of it because they can get it cheaper. Ok, so they may be able to get it at a lower price, but changing parts of the design affects other parts and, before you know it, it’s created a snowball effect of different impacts.

Think of the design as a well-oiled machine. If you start swapping out parts, it may not work properly or achieve the same output as required

It would be fine if you had the time to go back and reconsider the whole design, but you’ve only got two weeks until it’s on site. You feel like you’ve just gone back 20 steps, and all of that thought process and design methodology is quickly being unravelled. This is in addition to all the extra time spent redesigning when you should be looking at other things.

When you view the change holistically, its wider impact actually means its reducing value, not to mention increasing the risk of something going wrong either on site or, worse still, during use. Inevitably, these type of changes create delays to programme and increases costs.

This is modern day value engineering.

Originally, the intention of value engineering was to increase value by reducing cost while maintaining function. However, over the years, the process has become more about buying cheap, cutting corners and reducing quality. That, together with the increased complexity of construction facilities, means that this approach no longer achieves what it sets out to do. If you think about it, with contracts like Design and Build we’re designing things multiple times. Where’s the common sense in that?

By allowing the facility to drift away from its original purpose and need, value engineering actually perpetuates a performance gap. To reduce that gap in the facilities we hand over, we need to think more about outcomes and purposes.

We need to rethink construction projects so that we can make this additional process redundant.

Exploring new methods of procurement like Insurance Backed Alliancing allows the right people with the right knowledge and skills to be on board from the start. This means the facility can be confidently designed once to meet the outcomes of the project. Surely, this is a much better approach that really does provide better value for the client.

Changing procurement and contracts should be one of the top priorities for the industry. We desperately need a framework in place that works with all the great ideas, new ways of working and initiatives for change rather than against them. Without it, we will never realise the full benefits from them and we will never escape the shackles of inefficiency and unproductive.

If you would like to understand more about why we need to change procurement and the basics of Insurance Backed Alliancing please see my short presentation The Never Ending Story of Construction.

 

Our latest articles

Visqueen launches Ultimate Self Adhesive Membrane for hydrocarbon and VOC-contaminated sites

The construction industry faces growing challenges when building on increasingly complex brownfield sites. Alongside the need for effective waterproofing, developers and contractors must now address a wider range of ground contaminants, including hydrocarbons, volatile organic compounds (VOCs), and hazardous ground gases, while maintaining programme efficiency and installation quality. Against this backdrop, Visqueen has expanded its gas protection and waterproofing portfolio with the launch of Visqueen Ultimate Self Adhesive Membrane, a new hydrocarbon and VOC-resistant self-adhesive tanking membrane. Developed as the latest addition to the Visqueen non-foil gas barrier range, the new membrane combines proven gas barrier and waterproofing performance to help specifiers address multiple site challenges with a single solution.

Construction ProductsSponsored

Siderise: Helping to bridge the gap between Gateway 2 approval and on-site fire protection

While the new building safety regime hasn’t fundamentally changed what requirements higher-risk buildings (HRBs) must meet to comply with the Building Regulations, it has significantly increased the breadth, depth and volume of evidence that must be supplied to demonstrate this. As a result, project teams have had to adapt the way they work and even look beyond their roles to understand how their actions may impact the next Dutyholder in the chain. For specifiers, this can include considering what supporting services are offered with life safety-critical elements to enable correct design, installation and maintenance. Early engagement with manufacturer technical specialists can help identify any practical challenges that may arise onsite. Then, during construction, these services can help support the translation of design intent into reality so that buildings are safe for occupation.

Construction ProductsSponsored

RIBA CPD for Architects: Understanding Flooring Specification and Detailing

For architects and specifiers, flooring details can have a significant impact on the safety, accessibility, durability and overall performance of a building. Yet the technical considerations surrounding stairways, floor transitions, and floor finishes are not always straightforward.

RIBA CPDSponsored