The functions of a schedule of work

Nov 1, 2005 |Andrew Wilson

Andrew Wilson, NBS Scheduler coordinator, clears up our thinking on how schedules of work work. This article is paired by another, 'The structure of a schedule of work.

There is considerable scope for confusion in discussing schedules of work – usually arising from the lack of a generally accepted definition of structure and content, but also from disagreements over terminology, and whether inclusion of quantities within a schedule of work is valid. 

One aspect of the schedule of work that should not be in dispute is its general form and purpose, and for this article the essence of a schedule of work could hardly be simpler. It is a list – in this case a list, either in outline or detail, of building work. In common with any list it may be used for different purposes, by different people at different times. It may be accompanied by, or bound in with, other documents.

Supporting documents

Even simple building work can require a lot of description and the schedule of work is usually accompanied by other documents providing information supplementing the listed items, including:

  • drawings – to illustrate extent of the work;
  • schedules – itemized lists of particular product types, commonly doors, windows, ironmongery, finishes and decorations;
  • some form of specification – to describe the standards to which each category of work is to be carried out; and
  • preliminaries – to determine general requirements for the project as a whole,usually with reference to a particular standard form of building contract.

Differing uses throughout project

A simple list can serve a number of uses, and the schedule of work is no different. Together with the supporting documents, it may be used in the following ways:

  • Tender document.
  • Contract document.
  • Task list for work on site.
  • Check list for administration.
  • Record document.

Tender document

The purpose of the schedule of work at tendering stage is to provide sufficient description of the proposals to allow a number of independent building contractors (usually a minimum of three) to calculate fair and, hopefully, competitive prices for the work. In general this task will be undertaken by quantity surveyors (who may be employed directly by the contractor, and are then generally referred to as 'estimators'). They will price listed items to determine an overall cost.

The descriptions in the schedule of work must be unambiguous. They need not be complete in themselves, but may cross refer to the accompanying documents – particularly to the drawings. However, they must cover, at least in outline, all aspects of the work for which prices are required. Taken together the information provided must allow the contractor to identify all the materials needed and to calculate the quantities that will be required.

Contract document

Once a price has been agreed the schedule of work will form part of the legally binding 'contract documents' between employer (the building owner) and contractor.

Task list

The schedule of work, exactly as issued for tendering purposes, is also used on site by the contractor's workforce on a day to day basis to determine work required during construction. For use on site, the schedule of work and accompanying documents must not only identify the materials and allow calculation of quantities involved, but also give precise instructions on where all the materials are to be used and how they are to be fixed together. It should also set out an ordered arrangement of tasks to be carried out, in the correct sequence to achieve the desired end result.

Check list

The contract administrator (CA – who may be an architect, an architectural technologist, a building surveyor or other construction professional) is not necessarily the individual who wrote the schedule of work or produced the drawings. The CA will use the schedule of work to check that each of the listed items is being – or has been – carried out. The CA may also use the prices against checked items in the schedule of work to periodically calculate the value of the completed work.

Record document

The original schedule of work and supporting documents, together with descriptions of variations from the work originally intended, may be archived as an 'as built' document set for record purposes. In certain instances, if serious faults are later found, the schedule of work, as part of this document set, will again be studied in detail.

In general it is likely that the schedule of work must be read, and understood, by perhaps four or more sets of people who must each be able to use the document (and its supporting documents) to gain a particular understanding of the building. The extent to which these aims may be met depends largely on the structure of the schedule of work itself. There must be a methodology behind the description that relates closely to the type and extent of the work being carried out.

Our latest articles

Visqueen launches Ultimate Self Adhesive Membrane for hydrocarbon and VOC-contaminated sites

The construction industry faces growing challenges when building on increasingly complex brownfield sites. Alongside the need for effective waterproofing, developers and contractors must now address a wider range of ground contaminants, including hydrocarbons, volatile organic compounds (VOCs), and hazardous ground gases, while maintaining programme efficiency and installation quality. Against this backdrop, Visqueen has expanded its gas protection and waterproofing portfolio with the launch of Visqueen Ultimate Self Adhesive Membrane, a new hydrocarbon and VOC-resistant self-adhesive tanking membrane. Developed as the latest addition to the Visqueen non-foil gas barrier range, the new membrane combines proven gas barrier and waterproofing performance to help specifiers address multiple site challenges with a single solution.

Construction ProductsSponsored

Siderise: Helping to bridge the gap between Gateway 2 approval and on-site fire protection

While the new building safety regime hasn’t fundamentally changed what requirements higher-risk buildings (HRBs) must meet to comply with the Building Regulations, it has significantly increased the breadth, depth and volume of evidence that must be supplied to demonstrate this. As a result, project teams have had to adapt the way they work and even look beyond their roles to understand how their actions may impact the next Dutyholder in the chain. For specifiers, this can include considering what supporting services are offered with life safety-critical elements to enable correct design, installation and maintenance. Early engagement with manufacturer technical specialists can help identify any practical challenges that may arise onsite. Then, during construction, these services can help support the translation of design intent into reality so that buildings are safe for occupation.

Construction ProductsSponsored

RIBA CPD for Architects: Understanding Flooring Specification and Detailing

For architects and specifiers, flooring details can have a significant impact on the safety, accessibility, durability and overall performance of a building. Yet the technical considerations surrounding stairways, floor transitions, and floor finishes are not always straightforward.

RIBA CPDSponsored